Responsible for review and comment’s civil, structure and building drawing/ construction.
Qa/Qc : Inspection Test Plan Review/Comment/Approve, Site Inspection Civil (Concrete, Rebar,
Formwork, Soil And Misc.), Structure (Weld, Painting, Insulation And Misc.), Materials approve,
Handover Package (Review/Comment/Approve, Summary Check List With Site Procedure)
Supervisor : Safety (Review, Instruction, Present To Construction Team Approve), Schedule (Monitor
And Optimize), Cost (Change Review And Optimize), Construction Abilities.
Designer with Draftsman : Support Engineering Team For Check Option For All Discipline.
ประวัติการฝึกอบรม
ความสามารถ
ความสามารถทางภาษา
พูด (พอใช้) อ่าน (พอใช้) เขียน (พอใช้)
พูด (พอใช้) อ่าน (พอใช้) เขียน (พอใช้)
ไทย คำ/นาที อังกฤษ คำ/นาที
โครงการ / ผลงาน / เกียรติประวัติ / บุคคลอ้างอิง
Project : Soil Investigation Bore Hole 150 Ea. (Nov.2017~Aug.2018)
Setup site verification contractor (STS instruments co.,ltd) permit and issue to SAP
system present to TOP's AE,AGSI Team, Construction monitoring progress, Complete
work review handover document (Qa/qc, combination drawing to existing obstruction &
Misc.).
Project : CFP Support Center Renovation Project (Jan.2018~May.2018)
Setup site verification contractor (Prosper titan co. ltd) permit and issue to SAP system
present to TOP's AE,AGSI Team, Construction monitoring progress, Complete work
review handover document.
Project : GPSC Renovation Phase-1 Project (Feb.2019~Mar.2019)
Setup site verification contractor (Prosper titan co.,ltd) permit and issue to SAP system
present to TOP's AE,AGSI Team, Construction monitoring progress, Complete work
review handover document.
Project : GPSC Demolition & Renovation Phase-2 Project (Apr.2019~Aug.2019)
Demolition existing building and renovation
Setup site verification contractor (State construction co.,ltd) permit and issue to SAP
system present to TOP's AE,AGSI Team, Construction monitoring progress, Complete
work review handover document.
Project : MOF Dredging Work Project (Nov.2019~Sep.2020) Dredging soil volume
53,300 cu.m. (channel w:100m. l:950m.)
Setup site verification contractor (WEALTH Working Marine Co.,LTD.) permit and issue
to TOP's Team, Construction monitoring progress, Complete work review handover
document.
Project : CFP Initial Start-up Facilities Project (July.2020~Nov.2022) Civil work area
14,400 sq.m. (Site grading demolition existing paving modification building , excavation
soil improvement H:5m., Bund wall H:3m. L:380m., Road Asphalt, System, Drainage &
Misc.)
Setup site verification contractor (TRC construction Co.,LTD.) permit and issue to TOP's
Team, Construction monitoring progress, Complete work review handover document.
revised drawing. MTO, Presentation Soil Volume ETC.
Project : T-COT (2017) Contractor Wood (Foster Wheeler (Thailand) Limited)
Check Final Feed Handover Drawing To Contractor Design/Construction
Project : Piperack Jetty Route & Drainage System (2017)
Check Final Drawing From Contractor (Aerocon)
Project : Feed preliminary design to Contractor Wood (Foster Wheeler (Thailand) Limited) (Dec’
2018 ~ Nov’2021)
RHCU PILOT PLANT Contractor GCME (GC Maintenance and Engineering Company
Limited), (Aug’2022 to Nov’2022)
CATALYST WARE HOUSE And ETC. Contractor Wood (Worleyparsons (Thailand)
limited) (Nov’2022)