September 2019 - October 2020
Lenzing Project - 304 Industry Prachin Buri , Thailand
• Create Plotplan wastewater treatment and water plant for green field Project.
• Design and Route piping on paperback OSBL.
• Isometrics and GA production.
March 2018 – September 2019
BP Oil España S.A.U, BP Oil Refinería – Castellón, PROGRAMMA, Spain
• Revise Isometrics drawing.
• Working on GA drawing production stage.
August 2017 – March 2018
Hengyuan Refining Company Berhad, HRC Euro IV (M) Project, Malaysia EPC
• Recheck and develop pipe routing base on P&IDs with accordance to client engineering standards and specifications using 3D PDS software.
• Model equipment and comment on vendor drawing regarding nozzle orientation, nozzle projection, nozzle rating, and nozzle arrangement base on equipment data sheet, accessibility, operability and maintainability.
• Steam and condensate manifolds layout with accordance to steam tracing standards and specification.
• Closed out tag for 30% and 60% model review.
• Worked on Isometrics production stage.
June 2016 – July 2017
Thaioil Clean Fuel Project (Thaioil CFP), Thailand
• Site survey for update pipe existing for support CFP Project.
• Prepare Existing Facility Verification Report (EFVR) for support CFP Project.
• Prepare demolition GA. Drawing and Isometric drawing for early work scope.
• Site survey for Tie-in point.
• Plot plan for Khoa-Bo-Ya crude tanks farm with AutoCad Program.
• 3D Modelling by PDS Program Piping Modelling and Equipment Modelling.
• Piping GA drawing.