Project :
- FTP MCS (Fourth Transmission Pipeline Midline Compressor Station)
(Sanitary System, A/C System and Electrical System)
Responsible:
- Coordinate with customer (PTT) and consultant about technical specifications and documents for approval.
- Prepare the master schedule for planning the project.
- Design and prepare specification, proposal and other document.
- Provide sub-contractors and material for site work.
- Control site work and sub-contractors to comply with company standards in quality, schedule and cost.
- Estimate the mechanical system, sanitary system, A/C system, fire protection system and waste water
treatment system.
- Contact to the suppliers for request the quotation of mechanical system.
- Prepare the Bill of Quantity for submitting the variation order.
- Coordinate with customer and consultant about the variation order, omission and addition work, for negotiate.
Project :
- SWENSENS (M&E System)
Responsible:
- Coordinate with customer and designer about technical specifications and documents for approval.
- Prepare the master schedule for planning the project.
- Design and prepare specification, proposal and other document.
- Control site work and sub-contractors to comply with project standards in quality, schedule and cost.
Project :
- FTP MCS (Fourth Transmission Pipeline Midline Compressor Station)
(Sanitary System, A/C System and Electrical System)
Responsible:
- Coordinate with customer (PTT) and consultant about technical specifications and documents for approval.
- Prepare the master schedule for planning the project.
- Design and prepare specification, proposal and other document.
- Provide sub-contractors and material for site work.
- Control site work and sub-contractors to comply with company standards in quality, schedule and cost.
- Estimate the mechanical system, sanitary system, A/C system, fire protection system and waste water
treatment system.
- Contact to the suppliers for request the quotation of mechanical system.
- Prepare the Bill of Quantity for submitting the variation order.
- Coordinate with customer and consultant about the variation order, omission and addition work, for negotiate.
Project :
- Laguna Phuket Condominium
(Sanitary System, A/C System and Fire Protection System)
Responsible :
- Coordinate with customer and consultant about technical specifications and documents for approval.
- Prepare the master schedule for planning the project.
- Design and prepare specification, proposal and other document.
- Provide sub-contractors and material for site work.
- Control site work and sub-contractors to comply with company standards in quality, schedule and cost.
- Provide the project for bidding.
August, 2010 - February, 2014
Jardine Engineering Company Limited
Site Engineer
Salary : 30,000 Baht
Project :
- Park Ventures
(Sanitary System, A/C System and Fire Protection System)
- Mega Bangna
(Waste Water Treatment System, Irrigation System and Drainage System)
- Yothin-Burana School
(A/C System)
Responsible :
- Coordinate with customer and consultant about technical specifications and documents for approval.
- Design and prepare specification, proposal and other document.
- Control site work and sub-contractors to comply with company standards in quality, schedule and cost.
- Estimate the mechanical system, sanitary system, A/C system, fire protection system and waste water
treatment system.
- Contact to the suppliers for request the quotation of mechanical system.
- Prepare the Bill of Quantity for submitting the variation order.
- Coordinate with customer and consultant about the variation order, omission and addition work, for negotiate.
January, 2009 - July, 2010
Syntec Construction Public Company Limited
Site Engineer
Salary : 15,000 Baht
Project :
- Energy Complex (EnCo)
(Sanitary System, A/C System and Fire Protection System)
- Sky Walk Le Condominium
(Chiller Plant)
Responsible :
- Estimate the mechanical system, sanitary system, A/C system, fire protection system and waste water
treatment system.
- Contact to the suppliers for request the quotation of mechanical system.
- Prepare the Bill of Quantity for submitting the variation order.
- Review the technical specifications, prepare drawings and prepare documents for approval.
- Control site work and sub-contractors to comply with company standards in quality, schedule and cost.
ประวัติการฝึกอบรม
ความสามารถ
ความสามารถทางภาษา
พูด (ดีมาก) อ่าน (ดีมาก) เขียน (ดีมาก)
พูด (พอใช้) อ่าน (พอใช้) เขียน (พอใช้)
ไทย 45 คำ/นาที อังกฤษ 45 คำ/นาที
รถยนต์ ,รถจักรยานยนต์ ,
รถยนต์ ,
โครงการ / ผลงาน / เกียรติประวัติ / บุคคลอ้างอิง
เคยทำงานโครงการมาทั้งหมด 7 โครงการ
1. Energy Complex (EnCo)
(Sanitary System, A/C System and Fire Protection System)
2. Sky Walk Le Condominium
(Chiller Plant)
3. Park Ventures
(Sanitary System, A/C System and Fire Protection System)
4. Mega Bangna
(Waste Water Treatment System, Irrigation System and Drainage System)
5. Yothin-Burana School
(A/C System)
6. Laguna Phuket Condominium
(Sanitary System, A/C System and Fire Protection System)
7. FTP MCS (Fourth Transmission Pipeline Midline Compressor Station)
(Sanitary System, A/C System and Electrical System)